Pretium was engaged to provide an assessment and design for the replacement of existing incoming domestic water piping.
Other deficiencies were noted on-site during our review and building domestic water systems were upgraded to meet current municipal and code requirements. Pretium provided coordination and provision of new incoming domestic water for fire suppression and domestic water use, including a new incoming water room.
Backflow prevention was installed to meet cross-connection survey results, and incoming water services were relocated to avoid the use of a failing buried incoming line installed below the building.
To deliver this project, Pretium completed the following measures:
Condition Assessment
Design and Specifications
Tendering
Contract Administration and Construction Review
Client Benefits
Pretium was able to work with the project team to complete the work while the building was fully occupied. This included assisting with managing occupant expectations and working with the contractor to schedule and phase the work to minimize impact.
During construction, it was discovered that an existing incoming domestic water line serving the building had been relocated and abandoned without any public record. There was a planned eight-hour water shutdown for final connections to be made, and this issue was discovered once the final connection was made.
Pretium worked immediately with the contractor and client to provide temporary water service and ultimately locate and connect to the unmarked piping. Pretium was in constant communication with the contractor and property manager during the unplanned additional work to maintain coordination and ensure the property was aware of challenges and solutions on site.