Arda Yapicioglu, P. Eng., MASc
Arda ensures that every client receives the highest standard of care, taking the necessary time to understand the project requirement while conforming to project budget in a timely manner.
Arda ensures that every client receives the highest standard of care, taking the necessary time to understand the project requirement while conforming to project budget in a timely manner.
Stephen’s mission statement is to work with honesty, dedication, and integrity; and to never stop learning.
The building upgrades required the relocation of existing mechanical services, and the addition of a sprinkler system, where no system was previously installed.
Pretium coordinated with the architect, contractor and the City, to provide separate incoming domestic water and fire suppression service lines in separate rooms, to optimize useable space in the existing building.
Additionally, existing gas-fired HVAC equipment was removed and replaced with variable refrigerant flow (VRF) heat pump systems which allowed for precise temperature control in multiple office and treatment spaces.
Client Benefits
From the initial project planning stages, our team was involved with coordinating space planning and site service requirements during the renovations.
This allowed for smooth project progression with coordination between multiple parties, ensuring the safety of building occupants through the installation of fire suppression systems.
Our expert team is here to help you achieve your goals.
Other deficiencies were noted on-site during our review and building domestic water systems were upgraded to meet current municipal and code requirements. Pretium provided coordination and provision of new incoming domestic water for fire suppression and domestic water use, including a new incoming water room.
Backflow prevention was installed to meet cross-connection survey results, and incoming water services were relocated to avoid the use of a failing buried incoming line installed below the building.
Client Benefits
During construction, it was discovered that an existing incoming domestic water line serving the building had been relocated and abandoned without any public record. There was a planned eight-hour water shutdown for final connections to be made, and this issue was discovered once the final connection was made.
Pretium worked immediately with the contractor and client to provide temporary water service and ultimately locate and connect to the unmarked piping. Pretium was in constant communication with the contractor and property manager during the unplanned additional work to maintain coordination and ensure the property was aware of challenges and solutions on site.
Our expert team is here to help you achieve your goals.
New piping upgrades were completed, extending through three buildings to complete an ongoing phased central boiler plant expansion project. Hydronic systems were installed and updated to allow for connection into a recently installed central condensing boiler plant. Building upgrades included the removal of individual boiler systems and gas–fired, domestic hot water heaters for replacement with heat exchangers and piping tied into the central boiler plant in one of the three buildings.
Pretium’s involvement began with an application and award to a public tender for this hydronic system upgrade. The RFP included a general concept for the application of a second phase of construction for heating plant consolidation. Pretium performed extensive site reviews and documentation for pipe routing through existing operating buildings.
Pretium acted as the prime consultant on the project and coordinated in-house structural engineering review for new and updated equipment. We worked with an external electrical engineering firm to coordinate the electrical requirements for new and removed mechanical systems. A complete and coordinated set of bid documents were presented to Laurier University’s procurement group for public tendering through the school’s formal channels. We aided in contractor site reviews and the tendering process.
Upon award of construction, Pretium coordinated and organized a pre-construction meeting, outlining the roles and responsibilities of all parties. Ongoing site reviews and coordination took place during project construction. During the final balancing of the system, it was noted that design flows were not achieved at remote building locations. Pretium took the lead and chaired a meeting between the university stakeholders and the Phase One design engineers to coordinate changes to the base building systems. The proposed changes were accepted by base building engineers and the revisions were implemented.
Client Benefits
Project construction took place on an active university campus at the height of the COVID-19 pandemic. Project staffing, access, protection, and building protocols were changing constantly. Pretium worked closely with the University project managers to manage project timelines and adjust schedules to meet continually updating building access requirements, including complete lockdowns.
Following project completion, Pretium corresponded with the University periodically to answer questions regarding system operation and to help fine tune individual system components as the building operated in each of its first four seasons.
Our expert team is here to help you achieve your goals.
Robin is an industry professional with high standards of integrity specializing in mechanical building systems with technical software abilities, attention to detail and effective communication skills. His aim is to deliver exceptional customer service to our clients while looking after the project deliverables.
Mechanical Engineering allows us to play a key role in overall building performance with significant potential for meeting or exceeding energy reduction targets. It has always been a goal of Jeff’s to provide design solutions for clients which meet the highest standards for effective building operation while constantly striving to reduce energy consumption. With experience in a broad range of building sectors and project roles, he is always eager to apply his knowledge of Energy, HVAC, Plumbing, Drainage, and Fire Protection design to each new project. Every project is
treated as a new opportunity for design innovation and collaboration with stakeholders to ensure immediate design goals are met, while integrating long term strategy into each decision.